Draft Layout Plan Out for NAINA (Navi Mumbai Airport Influence Notified Area)

Last week NAINA disclosed draft for Interim Development Plan (IDP) for NAINA area. Find the details below :
NAINA comprises 270 revenue villages from Uran, Panvel, Karjat, Khalapur, and Pen Talukas of Raigad district and Thane Taluka of Thane district of Maharashtra. Out of which, 217 are full revenue villages. Remaining 54 are part revenue villages. Together, it has an area of approximately 56,172 ha (561sq.km).
Procedure for preparation of Interim Development Plan for NAINA as per MR&TP Act, 1966

MR&TP Act,
1966 Clause No.

Description

Date/ Due date
40 (1) (b)
Appointment of SPA for Notified Area
10-01-13
23  (1)
Date of Declaration of Intention for preparation of DP
12-05-14
32/25
Carry out survey and Prepare Existing Land Use (ELU)
15-07-14
32/26(1)
Publish a Notice, Prepare & Publish Draft IDP
15-08-14
32/28(1)
Consideration of suggestion objection
4 Months

•    Receiving of Suggestion/ Objection
15-09-14
32/28(2)
•    SPA to constitute Planning Committee (PC)
15-09-14

•    SPA to Forward Suggestion/ Objection to PC
15-09-14
32/28(3)
•    PC to give hearing  & prepare Report and submit to SPA
15-11-14

•    SPA to incorporate PC Report
15-12-14

32/30(1)
Submission of Draft IDP along with list of modification to Government
for approval

09-01-15

Highlights :

Infrastructure by CidcoCIDCO has developed Navi Mumbai and has vast experience in city development. CIDCO will take up construction and development of infrastructure works i.e. roads, water supply, sewerage, drainage.

Metro Railit is proposed  to extend the Mankhurd- Vashi- Belapur -NMIA-Panvel metro line into Interim Development Plan of NAINA

Suburban Rail Connectivity : Existing Diva-Panvel line and Proposed Panvel-Karjat-Khopoli and Panvel-Rasayani Sub-Urban Corridor along Konkan Railway

Important  transport  links of the IDP Area are Mumbai  Trans Harbour  Link (MTHL),  Mumbai-Vadodara  Spur, and Navi MUmbai International Airport.

Road NetworkProject Area with road network having RoWs for Sub-Arterials as 60m and 45m, sector roads and local access roads as 35m and 27m and 20m respectively.

Five Type of Zones

N1:  Predominantly  Residential:  The zone is aimed  at promoting  residential  townships  and support social infrastructure.  Compatible functions to that of residential development  would be permitted in N1.


N2: Growth Centre: The zone is aimed to promote commercial and business activities.


N3: Mixed Use Zone: The zone is aimed to promote mixed use activities, which can be located along areas of higher accessibility where land uses and activities related to public and economic importance can be located. 

N4: Urban Village: The zone around 200m of existing inhabitated Gaothans.

N5: Recreational Zone: The zone is aimed to promote open spaces and recreational activities


Sectoral Numbering to the area as we seen in Navi Mumbai :

The  IDP  area  is divided  into  te(10)  sectors.  The  division  of sectors  is based  on  the  existing  and proposed  physical features such as rivers, railway line, proposed  and existing roads. The sectors were divided considering the geographical area and population. The average area of each sector is 350 Ha. The estimated population of each sector is approximately 60,000

Source of water

Hetawane, Morbe, Proposed Kondhane & Balganga.

Sawage Collection & Recycling :  

The Sewage Collection  and recycling system is planned and designed to collect, treat, and recycle all the domestisewerage and industrial  effluent generated  from the IDP Area.

Land Sharing & Acquisition

The ownerdeveloper  will retain 60% of the land and 40 % land shall be surrendered  to  SPA-NAINA  free  of  cost  by  consent  agreement for  providing  roads,  open spaces, amenities and growth centre. The permissible FSI for the entire plot will be 1.00, which can be consumed on the 60 % of retained land resulting net FSI of 1.7 for the retained land.  If more than 40% land area is affected by reservations, landowner is to be compensated for loss of land in excess of 40% by allotting alternative land elsewhere s within same sector.

Development Plan :

Interim Development Plan for NAINA Area  has  been  divided  into  five categories:

1. Gaothan,  
2. Urban Villages,
3. NAINA-Scheme
4. Non-NAINA Scheme
5. Special Township Scheme

1. Gaothans are built areas it is expected that mostly redevelopment proposals will come for approval.   No FSI is proposed; instead built-form will be controlled by footprint and number of storey. Existing footprint will have to be retained and maximum two storeys are permissible including ground floor.
2. Urban Villages: Urban villages are areas of 200 m around existing inhabited gaothans as marked on the IDP. As per the existing MMR Regional Plan these areas are permitted an FSI of 1 and building height of 13.5  m.  
3. NAINA-Scheme:  The minimum area required for participating in NAINA scheme shall be 10 ha and  40% land will be surrendered to SPA-NAINA free of cost. Developer will be allowed to use FSI of entire land  on balance  60%  of retained  land. 
4. Individual  Plots (Non- NAINA Scheme): The FSI permissible for such developments will be 0.5 and layout regulations as per Standardized Regulations for DCPR for RP are applicable
5. Special Township Scheme: In case of already approved schemes Development Charges payable or paid as per Chapter VI-A will be payable by the developer. In case of new proposals developer will have to surrender 15% land as decided by SPA-NAINA. This 15% will be exclusive of IDP reservations if any.

Fees, Charges and Premiums for Builders
 Development charge: The development charge is proposed to be increased by 5 times the existing rates prescribed in MR&TP Act

Offsite City Service Delivery Charges (OCSDC): These are charges framed by SPA-NAINA, payable to SPA-NAINA by persons seeking development permission who would be using the city-level physical and social infrastructure developed by SPA-NAINA without contributing any land to SPA-NAINA.
NAINA – Infrastructure Timelines
Work/Activity
Start – Completion Period
Land Acquisition
2015-2016
Power
2016-2020
Solid Waste Management
2016-2020
Water Supply
2016-2024
Sewerage System
2016-2024
Drainage
2016-2024
Roads
2016-2024
Metro
2024-2028
Sub Urban Railway
2016-2020
Open Space
2016-2021
Public Infrastructure
2015-2019